Development of Water and Soil Resources along the Southern Course of the Aras river ...
Project name: Development of Water and Soil Resources along the Southern Course of the Aras river (Irrigation and Drainage Main Network of Karamabad Project)
Completed
2018/09/30
2019/11/27
Manager

West Azerbaijan Regional Water Company  

Goals
  • Supplying the agricultural water demands of 23 villages in a 22,300 hectare area along the southern course of The Aras; 
  • Utilizing Iran's water right (approximately 112 million cu. m); 
Schedule

1st and 2nd Phase Studies and supervision (3rd Phase)  

Executive Actions
  • Irrigation method:  Semi-portable sprinkler, center-pivot, and localized irrigation (drip tape) systems;
  • Length of the transmission line: 21 km
  • Transmission line diameter: 2000 mm, steel pipe
  • The length of the main line of the distribution network in nine construction units; 260 km
  • Pipe diameter: 450–20000 mm, steel, GRP, and PE pipes
  • Pumping stations in the network: 5
  • Pumping stations on the transmission line: 3
  • Power consumption: 35 MW
Geography Location

Poldasht and Shut Cities, West Azerbaijan Province, Iran