Friday Apr 19, 2024
Management Contractor of the Irrigation and Drainage Subnetworks in Ilam Province
Project name: Management Contractor of the Irrigation and Drainage Subnetworks in Ilam Province
Completed
2018/10/12
2019/11/27
Manager

West and Northwest of Iran Irrigation and Drainage Subnetwork Plan Administrator 

Goals
  • Economic promotion of the agricultural sector;
  • Encouraging population growth in the area through economic incentives;
  • Reducing Iran's economic vulnerability to external political challenges through endogenous growth;
  • Economic growth in the local agricultural sector;
Schedule

Management Contractor 

Executive Actions
  • Doiraj project : 7585 hectares;
  • Kangir project : 1850 hectares;
  • Meymeh project : 2700 hectares;
  • Garmsiri project : 17559 hectares;
Geography Location

Ilam Province, Iran